Explore the decision logEvery decision records why it was made and which alternatives were considered. Follow a link in the Source column to the meeting where the decision was taken.


The decision log collects all project decisions in one place. Weekly minutes record the discussion; this page records the result, so the reasoning is still available after the project has ended.

Overview

ID Decision Week Status
D-01 Additional language versions move to a follow-up project 1 Status: green, Active
D-02 Existing URLs are kept where possible, changed URLs get redirects 2 Status: green, Active
D-03 High-traffic pages are migrated first 4 Status: green, Active
D-04 QA prepares test cases in parallel with development 4 Status: green, Active
D-05 Additional technical requirements take priority over dependent QA work 5 Status: neutral, Superseded by D-06
D-06 Development tasks that unblock QA take priority 6 Status: green, Active
D-07 Launch stays in week 10, with a go/no-go decision in week 9 6 Status: green, Active

Decisions in detail

D-01: Additional language versions move to a follow-up project

Context: The original idea included an English and a German version of the new website at launch.
Alternatives considered: Launch both languages together; launch with machine-translated content.
Rationale: Translating and reviewing all migrated pages would add several weeks. Launching on time with one language and complete content was rated more important.
Decided by: Steering committee · Source: Project kick-off, week 1

D-02: Existing URLs are kept where possible, changed URLs get redirects

Context: Many external sites and search engines link to pages of the current website.
Alternatives considered: A completely new URL structure without redirects.
Rationale: Broken links would hurt search rankings and user experience after the launch. A redirect list is maintained by the Content workstream and implemented during cutover.
Decided by: Project manager together with Development and Content · Source: Planning workshop, week 2

D-03: High-traffic pages are migrated first

Context: Content migration started in week 4 with about 40 pages in scope.
Alternatives considered: Migration by site section; migration in alphabetical order.
Rationale: If the schedule comes under pressure, the most important pages are already available on the new site.
Decided by: Content lead · Source: Weekly meeting, week 4

D-04: QA prepares test cases in parallel with development

Context: QA could only start testing once the first development tasks were finished.
Alternatives considered: Start preparing tests after development is complete.
Rationale: Preparing test cases early shortens the QA phase and helps clarify requirements.
Decided by: Project manager · Source: Weekly meeting, week 4

D-05: Additional technical requirements take priority over dependent QA work

Context: New technical requirements were identified in week 5 and increased the development effort.
Alternatives considered: Move the new requirements to after the launch.
Rationale: The requirements affect core functions of the website and could not be postponed.
Decided by: Development lead · Source: Weekly meeting, week 5
Status: Superseded by D-06 in week 6, because QA was increasingly blocked.

D-06: Development tasks that unblock QA take priority

Context: By week 6, several test cases could not be executed because the related development tasks were still open.
Alternatives considered: Continue with the order from D-05; add external developers.
Rationale: Every blocked test case moves the risk closer to the launch date. Unblocking QA first keeps testing and development running in parallel.
Decided by: Project manager with Development lead · Source: Weekly meeting, week 6

D-07: Launch stays in week 10, with a go/no-go decision in week 9

Context: The delays in development and QA raised the question of whether the launch date can be kept.
Alternatives considered: Postpone the launch by two weeks now.
Rationale: The remaining buffer is still sufficient if D-06 takes effect. A fixed go/no-go decision in week 9 gives a clear checkpoint without moving the date too early.
Decided by: Steering committee · Source: Weekly meeting, week 6