| Meeting Title | Weekly Project Meeting |
| Date | Week 4 |
| Time | 10:00–10:45 |
| Location | Project room / MS Teams |
| Facilitator | Project manager |
| Note Taker | Content lead |
Participants
Attendees
- Project manager
- Development lead
- Content lead
- UX lead (web agency)
- QA lead
Absent
- None
Project data
| Area | Total number of tasks | Completed | Planned hours to date | Actual hours to date | Week | Progress (%) |
| UX | 20 | 14 | 100 | 95 | 4 | 70 |
| Development | 65 | 40 | 390 | 385 | 4 | 61.538461538462 |
| Content | 35 | 22 | 140 | 135 | 4 | 62.857142857143 |
| QA | 25 | 5 | 100 | 40 | 4 | 20 |
| Launch | 10 | 3 | 50 | 4 | 30 | |
| Total | 155 | 84 | 780 | 655 | 54.193548387097 |
Agenda
- Status of the UX concept
- Start of development and content migration
- Test preparation
Discussion
UX
The UX concept is largely complete. Final feedback from the stakeholder review is being incorporated by the web agency.
Development and content
The technical foundations are being implemented as planned. Content migration has started. The team discussed the order of migration and agreed to begin with the pages that receive the most traffic.
Outcome / DecisionHigh-traffic pages are migrated first. See D-03.
QA
QA can only start testing once the first development tasks are finished. To avoid losing time, test cases will be written in advance.
Outcome / DecisionQA prepares test cases in parallel with development. See D-04.
Action Items
| Action | Owner | Due | Status |
| Rank pages in the content inventory by traffic | Content lead | Week 4 | Status: green, Done |
| Prepare the first set of test cases | QA lead | Week 5 | Status: green, Done |
Risks and dependencies
- QA depends on completed development tasks.
- No major deviations from the plan at this stage.