Meeting Title Weekly Project Meeting
Date Week 5
Time 10:00–10:45
Location Project room / MS Teams
Facilitator Project manager
Note Taker Content lead

Participants

Attendees

Absent

  • UX lead (web agency)


Project data

AreaTotal number of tasksCompletedPlanned hours to dateActual hours to dateWeekProgress (%)
UX2216110108572.727272727273
Development7347435455564.383561643836
Content3828150140573.684210526316
QA30912065530
Launch1226015516.666666666667
Total17510287578358.285714285714

Agenda

  • New technical requirements
  • Start of QA activities
  • Launch preparation

Discussion

Development

Additional technical requirements were identified for the contact forms and the search function. They increase the development effort for the coming weeks. Postponing them until after the launch was discussed and rejected, because both functions are core parts of the website.

Outcome / DecisionThe additional technical requirements take priority over dependent QA work. See D-05.


QA

The first QA activities have started. Several test cases cannot be executed yet, because the related development tasks are still open.

Launch

Initial launch preparation has started with a first draft of the go-live checklist.

Action Items

Action Owner Due Status
Estimate the effort for the new requirements Development lead Week 5 Status: green, Done
List test cases blocked by open development tasks QA lead Week 6 Status: green, Done
Draft the go-live checklist Project manager Week 6 Status: yellow, In progress

Risks and dependencies

  • Open development tasks are delaying parts of QA.
  • Further delays could affect launch preparation.