Minutes:Weekly Project Meeting/Week 4: Difference between revisions

Test>WikiSysop
Journey 3: decisions and communication
Meryam Sahin (talk | contribs)
No edit summary
 
Line 13: Line 13:
|-
|-
|'''Facilitator'''
|'''Facilitator'''
|[[User:H2852179366|Project manager]]
|[[User:S7537546782|Project manager]]
|-
|-
|'''Note Taker'''
|'''Note Taker'''
|[[User:H1366711166|Content lead]]
|[[User:H8556541395|Content lead]]
|}
|}


== Participants ==
== Participants ==
=== Attendees ===
=== Attendees ===
* [[User:H2852179366|Project manager]]
* [[User:S7537546782|Project manager]]
* [[User:U4882260722|Development lead]]
* [[User:P2181372639|Development lead]]
* [[User:H1366711166|Content lead]]
* [[User:H8556541395|Content lead]]
* UX lead (web agency)
* UX lead (web agency)
* QA lead
* QA lead
Line 60: Line 60:
|-
|-
|Rank pages in the content inventory by traffic
|Rank pages in the content inventory by traffic
|[[User:H1366711166|Content lead]]
|[[User:H8556541395|Content lead]]
|Week 4
|Week 4
|<status color="green" light="true">Done</status>
|<status color="green" light="true">Done</status>
Line 73: Line 73:
* QA depends on completed development tasks.
* QA depends on completed development tasks.
* No major deviations from the plan at this stage.
* No major deviations from the plan at this stage.

Latest revision as of 10:27, 19 November 2026

Meeting Title Weekly Project Meeting
Date Week 4
Time 10:00–10:45
Location Project room / MS Teams
Facilitator Project manager
Note Taker Content lead

Participants

Attendees

Absent

  • None


Project data

AreaTotal number of tasksCompletedPlanned hours to dateActual hours to dateWeekProgress (%)
UX201410095470
Development6540390385461.538461538462
Content3522140135462.857142857143
QA25510040420
Launch10350430
Total1558478065554.193548387097

Agenda

  • Status of the UX concept
  • Start of development and content migration
  • Test preparation

Discussion

UX

The UX concept is largely complete. Final feedback from the stakeholder review is being incorporated by the web agency.

Development and content

The technical foundations are being implemented as planned. Content migration has started. The team discussed the order of migration and agreed to begin with the pages that receive the most traffic.

Outcome / DecisionHigh-traffic pages are migrated first. See D-03.


QA

QA can only start testing once the first development tasks are finished. To avoid losing time, test cases will be written in advance.

Outcome / DecisionQA prepares test cases in parallel with development. See D-04.


Action Items

Action Owner Due Status
Rank pages in the content inventory by traffic Content lead Week 4 Status: green, Done
Prepare the first set of test cases QA lead Week 5 Status: green, Done

Risks and dependencies

  • QA depends on completed development tasks.
  • No major deviations from the plan at this stage.