Meryam Sahin (talk | contribs) No edit summary |
Meryam Sahin (talk | contribs) No edit summary |
||
| Line 25: | Line 25: | ||
|- | |- | ||
|'''Note Taker''' | |'''Note Taker''' | ||
|[[User:H1366711166|Laura Fitzgerald]] | |Content Lead: [[User:H1366711166|Laura Fitzgerald]] | ||
|} | |} | ||
== Participants == | == Participants == | ||
=== Attendees === | === Attendees === | ||
* [[User:H2852179366|Kenneth Frye]] | * Project Manager: [[User:H2852179366|Kenneth Frye]] | ||
*[[User:U4882260722|Evelyn Shaffer]] | *Development Lead: [[User:U4882260722|Evelyn Shaffer]] | ||
* [[User:H1366711166|Laura Fitzgerald]] | * Content Lead: [[User:H1366711166|Laura Fitzgerald]] | ||
* UX lead (web agency) | * UX lead (web agency) | ||
* QA lead | * QA lead | ||
| Line 66: | Line 66: | ||
|- | |- | ||
|Reorder the development backlog by QA dependency | |Reorder the development backlog by QA dependency | ||
|[[User:U4882260722| | |Development lead: [[User:U4882260722|Evelyn Shaffer]] | ||
|Week 6 | |Week 6 | ||
|<status color="neutral" light>In progress</status> | |<status color="neutral" light>In progress</status> | ||
| Line 76: | Line 76: | ||
|- | |- | ||
|Prepare criteria for the go/no-go decision | |Prepare criteria for the go/no-go decision | ||
|[[User:H2852179366| | |Project manager: [[User:H2852179366|Kenneth Frye]] | ||
|Week 8 | |Week 8 | ||
|<status color="neutral" light>Planned</status> | |<status color="neutral" light>Planned</status> | ||
|- | |- | ||
|Publish the week 6 project update in the blog | |Publish the week 6 project update in the blog | ||
|[[User:H2852179366| | |Project manager: [[User:H2852179366|Kenneth Frye]] | ||
|Week 6 | |Week 6 | ||
|<status color="neutral" light>Done</status> | |<status color="neutral" light>Done</status> | ||
Revision as of 13:27, 5 November 2026
Follow the decisionsThe decisions taken in this meeting are highlighted and linked to the decision log, where the reasoning is kept for later.
| Meeting Title | Weekly Project Meeting |
| Date | Week 6 |
| Time | 10:00–10:45 |
| Location | Project room / MS Teams |
| Facilitator | |
| Note Taker | Content Lead: Laura Fitzgerald |
Participants
Attendees
- Project Manager: Kenneth Frye
- Development Lead: Evelyn Shaffer
- Content Lead: Laura Fitzgerald
- UX lead (web agency)
- QA lead
Absent
- None
Project data
| Area | Total number of tasks | Completed | Planned hours to date | Actual hours to date | Week | Progress (%) |
| UX | 24 | 18 | 120 | 115 | 6 | 75 |
| Development | 80 | 52 | 480 | 510 | 6 | 65 |
| Content | 40 | 31 | 160 | 145 | 6 | 77.5 |
| QA | 35 | 12 | 140 | 95 | 6 | 34.285714285714 |
| Launch | 15 | 4 | 80 | 35 | 6 | 26.666666666667 |
| Total | 194 | 117 | 980 | 900 | 60.309278350515 |
Agenda
- Development effort and blocked test cases
- Review of the priority decision from week 5
- Launch date
Discussion
Development and QA
Development effort is now above plan. The list of blocked test cases shows that QA is increasingly waiting for development. The team agreed to change the priorities set in week 5.
Outcome / DecisionDevelopment tasks that unblock QA take priority. This replaces the decision from week 5. See D-06.
Launch date
The team discussed whether the launch should be postponed. The remaining buffer is still sufficient if the new priorities take effect. The steering committee confirmed the date in a short call after the meeting.
Outcome / DecisionThe launch stays in week 10. A go/no-go decision is taken in week 9. See D-07.
Action Items
| Action | Owner | Due | Status |
| Reorder the development backlog by QA dependency | Development lead: Evelyn Shaffer | Week 6 | Status: neutral, In progress |
| Re-run blocked test cases as soon as the tasks are completed | QA lead | Week 7 | Status: neutral, Planned |
| Prepare criteria for the go/no-go decision | Project manager: Kenneth Frye | Week 8 | Status: neutral, Planned |
| Publish the week 6 project update in the blog | Project manager: Kenneth Frye | Week 6 | Status: neutral, Done |
Risks and dependencies
- Development effort is above plan.
- QA remains dependent on development.
- Delays in QA may affect the launch date.