Follow the decisionsThe decisions taken in this meeting are highlighted and linked to the decision log, where the reasoning is kept for later.
| Meeting Title | Weekly Project Meeting |
| Date | Week 6 |
| Time | 10:00–10:45 |
| Location | Project room / MS Teams |
| Facilitator | |
| Note Taker | Content Lead: Janna Britt |
Participants
Attendees
- Project Manager: Austin Rutledge
- Development Lead: Shay Christian
- Content Lead: Janna Britt
- UX lead (web agency)
- QA lead
Absent
- None
Project data
| Area | Total number of tasks | Completed | Planned hours to date | Actual hours to date | Week | Progress (%) |
| UX | 24 | 18 | 120 | 115 | 6 | 75 |
| Development | 80 | 52 | 480 | 510 | 6 | 65 |
| Content | 40 | 31 | 160 | 145 | 6 | 77.5 |
| QA | 35 | 12 | 140 | 95 | 6 | 34.285714285714 |
| Launch | 15 | 4 | 80 | 35 | 6 | 26.666666666667 |
| Total | 194 | 117 | 980 | 900 | 60.309278350515 |
Agenda
- Development effort and blocked test cases
- Review of the priority decision from week 5
- Launch date
Discussion
Development and QA
Development effort is now above plan. The list of blocked test cases shows that QA is increasingly waiting for development. The team agreed to change the priorities set in week 5.
Outcome / DecisionDevelopment tasks that unblock QA take priority. This replaces the decision from week 5. See D-06.
Launch date
The team discussed whether the launch should be postponed. The remaining buffer is still sufficient if the new priorities take effect. The steering committee confirmed the date in a short call after the meeting.
Outcome / DecisionThe launch stays in week 10. A go/no-go decision is taken in week 9. See D-07.
Action Items
| Action | Owner | Due | Status |
| Reorder the development backlog by QA dependency | Development lead: Shay Christian | Week 6 | Status: yellow, In progress |
| Re-run blocked test cases as soon as the tasks are completed | QA lead | Week 7 | Status: blue, Planned |
| Prepare criteria for the go/no-go decision | Project manager: Austin Rutledge | Week 8 | Status: blue, Planned |
| Publish the week 6 project update in the blog | Project manager: Austin Rutledge | Week 6 | Status: green, Done |
Risks and dependencies
- Development effort is above plan.
- QA remains dependent on development.
- Delays in QA may affect the launch date.