Follow the decisionsThe decisions taken in this meeting are highlighted and linked to the decision log, where the reasoning is kept for later.
Meeting Title Weekly Project Meeting
Date Week 6
Time 10:00–10:45
Location Project room / MS Teams
Facilitator
Note Taker Content Lead: Janna Britt

Participants

Attendees

Absent

  • None


Project data

AreaTotal number of tasksCompletedPlanned hours to dateActual hours to dateWeekProgress (%)
UX2418120115675
Development8052480510665
Content4031160145677.5
QA351214095634.285714285714
Launch1548035626.666666666667
Total19411798090060.309278350515

Agenda

  • Development effort and blocked test cases
  • Review of the priority decision from week 5
  • Launch date

Discussion

Development and QA

Development effort is now above plan. The list of blocked test cases shows that QA is increasingly waiting for development. The team agreed to change the priorities set in week 5.

Outcome / DecisionDevelopment tasks that unblock QA take priority. This replaces the decision from week 5. See D-06.


Launch date

The team discussed whether the launch should be postponed. The remaining buffer is still sufficient if the new priorities take effect. The steering committee confirmed the date in a short call after the meeting.

Outcome / DecisionThe launch stays in week 10. A go/no-go decision is taken in week 9. See D-07.


Action Items

Action Owner Due Status
Reorder the development backlog by QA dependency Development lead: Shay Christian Week 6 Status: yellow, In progress
Re-run blocked test cases as soon as the tasks are completed QA lead Week 7 Status: blue, Planned
Prepare criteria for the go/no-go decision Project manager: Austin Rutledge Week 8 Status: blue, Planned
Publish the week 6 project update in the blog Project manager: Austin Rutledge Week 6 Status: green, Done

Risks and dependencies

  • Development effort is above plan.
  • QA remains dependent on development.
  • Delays in QA may affect the launch date.