Meryam Sahin (talk | contribs) m 1 revision imported |
Meryam Sahin (talk | contribs) No edit summary |
||
| (One intermediate revision by one other user not shown) | |||
| Line 13: | Line 13: | ||
|- | |- | ||
|'''Facilitator''' | |'''Facilitator''' | ||
|[[User: | |[[User:S7537546782|Project manager]] | ||
|- | |- | ||
|'''Note Taker''' | |'''Note Taker''' | ||
|[[User: | |[[User:H8556541395|Content lead]] | ||
|} | |} | ||
== Participants == | == Participants == | ||
=== Attendees === | === Attendees === | ||
* [[User: | * [[User:S7537546782|Project manager]] | ||
* [[User: | * [[User:P2181372639|Development lead]] | ||
* [[User: | * [[User:H8556541395|Content lead]] | ||
* UX lead (web agency) | * UX lead (web agency) | ||
* QA lead | * QA lead | ||
| Line 58: | Line 58: | ||
|- | |- | ||
|Estimate the effort for the new requirements | |Estimate the effort for the new requirements | ||
|[[User: | |[[User:P2181372639|Development lead]] | ||
|Week 5 | |Week 5 | ||
|<status color="green" light="true">Done</status> | |<status color="green" light="true">Done</status> | ||
| Line 68: | Line 68: | ||
|- | |- | ||
|Draft the go-live checklist | |Draft the go-live checklist | ||
|[[User: | |[[User:S7537546782|Project manager]] | ||
|Week 6 | |Week 6 | ||
|<status color="yellow" light="true">In progress</status> | |<status color="yellow" light="true">In progress</status> | ||
| Line 76: | Line 76: | ||
* Open development tasks are delaying parts of QA. | * Open development tasks are delaying parts of QA. | ||
* Further delays could affect launch preparation. | * Further delays could affect launch preparation. | ||
Latest revision as of 13:49, 19 November 2026
| Meeting Title | Weekly Project Meeting |
| Date | Week 5 |
| Time | 10:00–10:45 |
| Location | Project room / MS Teams |
| Facilitator | Project manager |
| Note Taker | Content lead |
Participants
Attendees
- Project manager
- Development lead
- Content lead
- UX lead (web agency)
- QA lead
Absent
- UX lead (web agency)
Project data
| Area | Total number of tasks | Completed | Planned hours to date | Actual hours to date | Week | Progress (%) |
| UX | 22 | 16 | 110 | 108 | 5 | 72.727272727273 |
| Development | 73 | 47 | 435 | 455 | 5 | 64.383561643836 |
| Content | 38 | 28 | 150 | 140 | 5 | 73.684210526316 |
| QA | 30 | 9 | 120 | 65 | 5 | 30 |
| Launch | 12 | 2 | 60 | 15 | 5 | 16.666666666667 |
| Total | 175 | 102 | 875 | 783 | 58.285714285714 |
Agenda
- New technical requirements
- Start of QA activities
- Launch preparation
Discussion
Development
Additional technical requirements were identified for the contact forms and the search function. They increase the development effort for the coming weeks. Postponing them until after the launch was discussed and rejected, because both functions are core parts of the website.
Outcome / DecisionThe additional technical requirements take priority over dependent QA work. See D-05.
QA
The first QA activities have started. Several test cases cannot be executed yet, because the related development tasks are still open.
Launch
Initial launch preparation has started with a first draft of the go-live checklist.
Action Items
| Action | Owner | Due | Status |
| Estimate the effort for the new requirements | Development lead | Week 5 | Status: green, Done |
| List test cases blocked by open development tasks | QA lead | Week 6 | Status: green, Done |
| Draft the go-live checklist | Project manager | Week 6 | Status: yellow, In progress |
Risks and dependencies
- Open development tasks are delaying parts of QA.
- Further delays could affect launch preparation.