The checklist covers everything that has to happen between now and the weeks after the launch. Each item has an owner, a due week and a status, and links to the decisions and pages it depends on.
The go-live checklist is maintained by the project manager Kenneth Frye and reviewed in every weekly meeting. The launch is planned for week 10, with a go/no-go decision in week 9 (D-07).
Go/no-go criteria
The steering committee gives the go for the launch if all of the following criteria are met:
- All high-priority pages in the content inventory are migrated and approved.
- No critical defects are open.
- All redirects are tested.
- The legal pages are approved.
- Operations has accepted the handover.
Before the go/no-go decision (weeks 7–9)
| Task
|
Owner
|
Due week
|
Status
|
Related
|
| Draft the go-live checklist
|
Project manager Kenneth Frye
|
6
|
Status: neutral, Done
|
|
| Complete the redirect list for all changed URLs
|
Content lead Laura Fitzgerald
|
8
|
Status: neutral, In progress
|
Content inventory, D-02
|
| Approve legal pages (imprint, privacy policy, cookie settings)
|
Legal
|
8
|
Status: neutral, Done
|
Content inventory
|
| Configure analytics and cookie consent
|
Development lead Evelyn Shaffer
|
8
|
Status: neutral, In progress
|
|
| Run accessibility and performance tests
|
QA lead
|
9
|
Status: neutral, Planned
|
|
| Lower DNS TTL for the website domain
|
IT operations
|
9
|
Status: neutral, Planned
|
|
| Back up the current website
|
Development lead Evelyn Shaffer
|
9
|
Status: neutral, Planned
|
|
| Prepare go/no-go criteria
|
Project manager Kenneth Frye
|
8
|
Status: neutral, Planned
|
D-07
|
Go/no-go decision (week 9)
| Task
|
Owner
|
Due week
|
Status
|
Related
|
| Go/no-go meeting with the steering committee
|
Project manager
|
9
|
Status: neutral, Planned
|
D-07
|
| Content freeze on the current website
|
Content lead
|
9
|
Status: neutral, Planned
|
|
Cutover (week 10)
| Task
|
Owner
|
Due week
|
Status
|
Related
|
| Switch DNS to the new website
|
IT operations
|
10
|
Status: neutral, Planned
|
|
| Activate redirects
|
Development lead
|
10
|
Status: neutral, Planned
|
D-02
|
| Run smoke tests on all high-priority pages
|
QA lead
|
10
|
Status: neutral, Planned
|
Content inventory
|
| Announce the launch in the project blog
|
Project manager
|
10
|
Status: neutral, Planned
|
|
After the launch
| Task
|
Owner
|
Due week
|
Status
|
Related
|
| Monitor errors, broken links and performance for two weeks
|
Development lead
|
10–12
|
Status: neutral, Planned
|
|
| Sign off the operations handover
|
Project manager
|
12
|
Status: neutral, Planned
|
Operations handover
|
| Hold the project retrospective
|
Project team
|
12
|
Status: neutral, Planned
|
|
| Set the project wiki to read-only
|
Project manager
|
12
|
Status: neutral, Planned
|
|