The corporate website is being relaunched with a new user experience, a new technical platform and revised content. The project runs for ten weeks. The new website goes live in week 10.
Teams and responsibilities
| Workstream | Responsibility |
|---|---|
| UX | User research, information architecture, design concept |
| Development | Technical implementation, integrations, performance |
| Content | Content inventory, writing and migration of website pages |
| QA | Test cases, test execution, accessibility checks |
| Launch | Go-live preparation, cutover and handover to operations |
| Project management | Planning, status reporting, decisions and stakeholder communication |
An external web agency supports the UX and Development workstreams. Agency staff work directly in this project wiki and have no access to the other areas of the company wiki.
Phases and timeline
| Phase | Weeks | Status |
|---|---|---|
| Concept and UX | 1–4 | Status: green, Largely completed |
| Development | 3–8 | Status: orange, In progress, above plan |
| Content migration | 4–8 | Status: yellow, In progress |
| Quality assurance | 5–9 | Status: orange, In progress, partly blocked |
| Launch preparation and go-live | 5–10 | Status: yellow, Started |
The project is currently in week 6. The current figures for each workstream are on the project status page.