Current state of website launch

The analysis highlights trends, deviations, and correlations within the project.

Timeline

Line chart

Progress by area

Bar chart

Planned vs. Actual Effort

Bar chart

Key findings

  • Overall progress continues to increase, but only slightly.
  • QA and Launch are behind the other project areas.
  • Development effort is above plan.
  • Lower QA effort does not necessarily indicate positive progress: QA is partly blocked by unfinished Development tasks.