Current state of website launch
The analysis highlights trends, deviations, and correlations within the project.
Timeline
Progress by area
Planned vs. Actual Effort
Key findings
- Overall progress continues to increase, but only slightly.
- QA and Launch are behind the other project areas.
- Development effort is above plan.
- Lower QA effort does not necessarily indicate positive progress: QA is partly blocked by unfinished Development tasks.