Explore the go-live checklistThe checklist covers everything that has to happen between now and the weeks after the launch. Each item has an owner, a due week and a status, and links to the decisions and pages it depends on.
The go-live checklist is maintained by the project manager and reviewed in every weekly meeting. The launch is planned for week 10, with a go/no-go decision in week 9 (D-07).
Go/no-go criteria
The steering committee gives the go for the launch if all of the following criteria are met:
- All high-priority pages in the content inventory are migrated and approved.
- No critical defects are open.
- All redirects are tested.
- The legal pages are approved.
- Operations has accepted the handover.
Before the go/no-go decision (weeks 7–9)
| Task | Owner | Due week | Status | Related |
|---|---|---|---|---|
| Draft the go-live checklist | Project manager | 6 | Status: green, Done | |
| Complete the redirect list for all changed URLs | Content lead | 8 | Status: yellow, In progress | Content inventory, D-02 |
| Approve legal pages (imprint, privacy policy, cookie settings) | Legal | 8 | Status: green, Done | Content inventory |
| Configure analytics and cookie consent | Development lead | 8 | Status: yellow, In progress | |
| Run accessibility and performance tests | QA lead | 9 | Status: blue, Planned | |
| Lower DNS TTL for the website domain | IT operations | 9 | Status: blue, Planned | |
| Back up the current website | Development lead | 9 | Status: blue, Planned | |
| Prepare go/no-go criteria | Project manager | 8 | Status: blue, Planned | D-07 |
Go/no-go decision (week 9)
| Task | Owner | Due week | Status | Related |
|---|---|---|---|---|
| Go/no-go meeting with the steering committee | Project manager | 9 | Status: blue, Planned | D-07 |
| Content freeze on the current website | Content lead | 9 | Status: blue, Planned |
Cutover (week 10)
| Task | Owner | Due week | Status | Related |
|---|---|---|---|---|
| Switch DNS to the new website | IT operations | 10 | Status: blue, Planned | |
| Activate redirects | Development lead | 10 | Status: blue, Planned | D-02 |
| Run smoke tests on all high-priority pages | QA lead | 10 | Status: blue, Planned | Content inventory |
| Announce the launch in the project blog | Project manager | 10 | Status: blue, Planned |
After the launch
| Task | Owner | Due week | Status | Related |
|---|---|---|---|---|
| Monitor errors, broken links and performance for two weeks | Development lead | 10–12 | Status: blue, Planned | |
| Sign off the operations handover | Project manager | 12 | Status: blue, Planned | Operations handover |
| Hold the project retrospective | Project team | 12 | Status: blue, Planned | |
| Set the project wiki to read-only | Project manager | 12 | Status: blue, Planned |