Meryam Sahin (talk | contribs) Created page with "== Current state of website launch == The analysis highlights trends, deviations, and correlations within the project. Timeline<linechart>KW 32 ,18 KW 33, 19 KW 34, 24 KW 35, 14 KW 36, 42 </linechart> === Progress by area=== <barchart showvalues="false" width="600">UX, 75 Development, 65 Content, 77.5 QA, 34.3 Launch, 26.7</barchart> === Planned vs. Actual Effort === <barchart showvalues="false" width="600">---color:#1E3A8A label: Planned UX, 120 Development, 480 Cont..." |
Meryam Sahin (talk | contribs) No edit summary |
||
| Line 2: | Line 2: | ||
The analysis highlights trends, deviations, and correlations within the project. | The analysis highlights trends, deviations, and correlations within the project. | ||
Timeline<linechart>KW 32 , | === Timeline === | ||
KW 33, | <linechart>KW 32, 38 | ||
KW 34, | KW 33, 45 | ||
KW 35, | KW 34, 52 | ||
KW 36, | KW 35, 58 | ||
KW 36, 60 </linechart> | |||
=== Progress by area=== | === Progress by area=== | ||
| Line 35: | Line 36: | ||
* Development effort is above plan. | * Development effort is above plan. | ||
* Lower QA effort does not necessarily indicate positive progress: QA is partly blocked by unfinished Development tasks. | * Lower QA effort does not necessarily indicate positive progress: QA is partly blocked by unfinished Development tasks. | ||
Revision as of 14:24, 7 September 2026
Current state of website launch
The analysis highlights trends, deviations, and correlations within the project.
Timeline
Progress by area
Planned vs. Actual Effort
Key findings
- Overall progress continues to increase, but only slightly.
- QA and Launch are behind the other project areas.
- Development effort is above plan.
- Lower QA effort does not necessarily indicate positive progress: QA is partly blocked by unfinished Development tasks.