Keep stakeholders informedThe project blog translates the results of the weekly meetings into short updates for everyone outside the project team. Compare this post with the week 6 minutes and the decision log.
Testing has become the main focus of the project this week.
Where we stand. Overall, 60 percent of all project tasks are complete. Development is still above its planned effort, and several test cases are waiting for development tasks to be finished.
What we are changing. To keep testing on track, the team has changed its priorities: development tasks that unblock testing now come first. This replaces the approach we chose last week. You can read the reasoning in the decision log.
Launch date. The launch remains planned for week 10. A final go/no-go decision will be made in week 9.
The current figures are always available on the project status page.