Explore the project statusAll figures on this page are read directly from the project spreadsheet. When the team updates the spreadsheet, the status page follows automatically.


Status in week 6 of 10

Overall status
🟡 On track with risks
Development effort is above plan, and part of QA is waiting for open development tasks.
Overall progress
60.3 %

Completed tasks of all planned tasks
Effort to date
Actual hours
900 h
Compared with hours planned to date
Planned launch
Week 10
Current phase: implementation and QA

Workstreams

UX
75 %

The concept is largely complete. Final feedback is being incorporated.
Development
65 %

Additional technical requirements have increased the effort. Several open tasks block downstream activities.
Content
77.5 %

High-traffic pages have been migrated first. The remaining pages follow the content inventory.
QA
34.3 %

Several test cases cannot be executed yet because the required development tasks are still open.
Launch
26.7 %

Launch preparation has started and depends on progress in Development and QA.
Overall progress by week (%)
Line chart
Planned vs. actual hours to date
Bar chart

Risks and dependencies

  • Development effort is above plan, mainly because of additional technical requirements.
  • QA depends on open development tasks. Further delays in QA would affect the launch date.
  • Launch preparation can only be completed once QA has signed off.

The background to these points is recorded in the weekly project minutes. The latest one is week 6.