| == Current state of website launch ==
| | #REDIRECT [[Project status]] |
| The analysis highlights trends, deviations, and correlations within the project.
| |
| | |
| === Timeline ===
| |
| <linechart>KW 32, 38
| |
| KW 33, 45
| |
| KW 34, 52
| |
| KW 35, 58
| |
| KW 36, 60 </linechart>
| |
| | |
| === Progress by area===
| |
| <barchart showvalues="false" width="300">UX, 75
| |
| Development, 65
| |
| Content, 77.5
| |
| QA, 34.3
| |
| Launch, 26.7</barchart>
| |
| | |
| === Planned vs. Actual Effort ===
| |
| <barchart showvalues="false" width="300">---color:#1E3A8A label: Planned
| |
| UX, 120
| |
| Development, 480
| |
| Content, 160
| |
| QA, 140
| |
| Launch, 80
| |
| ---color:#F97316 label: Actual
| |
| UX, 115
| |
| Development, 510
| |
| Content, 145
| |
| QA, 95
| |
| Launch, 35</barchart>
| |
| | |
| === Key findings ===
| |
| | |
| * Overall progress continues to increase, but only slightly.
| |
| * QA and Launch are behind the other project areas.
| |
| * Development effort is above plan.
| |
| * Lower QA effort does not necessarily indicate positive progress: QA is partly blocked by unfinished Development tasks.
| |